| I | Pre-Treatment, Collection & Conveyance |
| 1 | Removing and re-laying of Gravity and Pressure manhole in RCC |
| 2 | Laying of Ductile Iron conveyance line for transfer of Recovered Water from CETP to Member Tanneries. |
| 3 | Installation of wireless monitoring system for all member tannery flow meter and TDS meter including cloud server. |
| II | Primary, Secondary & Tertiary Treatment |
| 4 | Conversion of receiving sump pump house in to filtrate effluent collection sump. |
| 5 | Construction of Additional Equalization 3000 KL Tank. |
| 6 | Control of odour in the Equalization Tank and Receiving Sump and installation of Vacuum Swing Adsorption (VSA) for generation of pure oxygen. |
| 7 | Up-gradation of Filter press feed pump with energy efficient pumps |
| 8 | Reduction of Hydrogen Sulphide in the Pre-Aeration Tank by using Original Hydrodynamic Reaction (OHR) Aerator. |
| 9 | Improvement of blower efficiency in Aeration Tank – I & II. |
| 10 | Conversion of MS Primary Clarifier, Secondary Clarifier & Re-Activated Clarifier Mechanisms with scrapper in to SS 316 L |
| 11 | Installation of Air Operating Diaphragm pump for chemical dosing |
| 12 | Extension of PCC (Power Control Centre) panel with building. |
| 13 | Sludge extraction pump with Lorry and Tractor Trailer |
| 14 | Construction of Approach road to Nitrification & De- nitrification tanks, Multiple Effect Evaporator, Secure Landfill System, Wood Storage Platform, Sludge drying platform and shed within the CETP plant. |
| 15 | Construction of cable trench in RCC and cable tray ladder type and supporting in SS304 including laying of armoures HT/LT XLPE cables. |
| 16 | Construction of Centralised Control and Monitoring Centre. |
| 17 | Centrifuge for dewatering of Aeration Tank Bio Sludge - 2nos. |
| III | RO & Evaporator |
| 18 | Improvement of PES UF membrane in to PVDF/Ceramic membrane to reduce backwash process. |
| 19 | Installation of 600 KLD RO followed by NF. |
| 20 | Construction of De-Nitrification Tank and Nitrification Tank and Fine Screen (250 m3/h). |
| 21 | Installation of 800 KLD Multiple Effective Evaporator with Boiler and ATFD. |
| 22 | Installation of Ammonia Removal plant by using Hydrophobic membrane for Evaporator condensate water. |
| 23 | Installation of Flue Gas Analyzer for Boiler. |
| 24 | Construction of Wood storage platform. |
| IV | Secure Land Fill System |
| 25 | Construction of paddle dryer shed, Sludge storage platform etc., (sludge storage platform and shed, paddle dryer (1 No) and other mechanical items (Tipper lorry 1 number only) for handling of CETP sludge) |
| V | Alternate power |
| 26 | Installation of 4MW Solar Energy @ 4.5crore per MW with an output of 1.8 Million units (AC) per annum per MW (7.2 Million units per year). |
| 27 | Installation of 1 ton/hr Solar Steam Generation |